BASIS · TEAM HUDDLE

FOR DAMIEN WINBERG AND JASON CARLOS

PAGE 1 OF 15

[basis-io]

Team huddle.

Project plan for the [basis-io] prototype, version 1.0.

Friday 16 October 2026

BASIS · TEAM HUDDLE

01 · WHY WE ARE HERE

PAGE 2 OF 15

Why we are here

Three things to agree.

1. Prototype build

Airlock

  • Upload portal
  • Redaction and tokenisation
  • Token key
  • Job number

Vault

  • Matching
  • Workflow

(Testing on dummy data.)

2. Roles and responsibilities

  • Dean · product build
  • Jason · SME, subject matter expert. Testing, and confirms usability of the product.
  • Damien · executive oversight

Changed on the call · 16 Oct

3. Timelines

Dates on slide 10.

Agreed on the call: two calls a week, prototype working in two to three weeks.

BASIS · TEAM HUDDLE

02 · ROLES AND RESPONSIBILITIES · AGREED

PAGE 3 OF 15

Roles and responsibilities · agreed 16 Oct

Who does what.

NameRoleStepsMilestone date
DeanProduct buildAzure and repo set up. Upload portal. Redaction and tokenisation with Presidio. Token key and job number. Agents on tokens. Vault matching and workflow.Agreed 16 Oct. Portal first, redaction and tokenisation for testing late next week.
JasonSME, subject matter expertSupplies the dummy client pack and the document types advisers send. Tests each piece as it lands. Confirms usability of the product.Agreed 16 Oct. Dummy data this week.
DamienExecutive oversightKeeps the build to APP, SOC 1 and 2 and ISO 27001. Brings the licensee view: what a licensee would accept and ask for.Agreed 16 Oct. Shareholders agreement to finalise.

Roles agreed on the call, 16 October. Milestone dates on slide 10.

BASIS · TEAM HUDDLE

03 · FIG.01 · PLATFORM SCHEMATIC · PROGRESS REPORT, 5 OCT 2026

PAGE 4 OF 15

[basis-io] platform schematic, Figure 1 from the progress report of 5 October 2026

BASIS · TEAM HUDDLE

04 · FIG.02 · THE SAME DRAWING · AIRLOCK AROUND EVERYTHING

PAGE 5 OF 15

Figure 1 with the Airlock around everything, the Vault in purple and a Compliance Workspace

BASIS · TEAM HUDDLE

05 · THE FIVE TASKS, IN ORDER

PAGE 6 OF 15

What gets built

Five tasks, in this order, tested on dummy data.

#TaskWhat it doesCompleted whenStatus
1Upload portalAdviser signs in, starts a job, uploads the SoAR (SOA request), the CPF (client profile) and the supporting documents. Simple enough to use without instructions.Working on dummy documents.Not started
2Redaction and tokenisationPresidio finds the PII in each document, redacts what is not needed and replaces the rest with tokens. One tokenised copy per document.Jason’s pack goes in; clean copies come out; nothing identifying left.Not started
3Token key and job numberThe key that maps tokens back to real values is written to the Key Store in Azure. A job number is issued and every file carries it.Key readable only by the Airlock; the Vault cannot read it.Not started
4Two agents, tokens onlyA local agent in the Airlock hands the tokenised files to the Vault agent, which runs on an LLM. They talk in tokens and job numbers.A full exchange with no real value crossing the line. At sign-off both agents retire and their markdown files sit in the Evidentiary Layer.Not started
5Matching and workflow in the VaultThe three sets are matched, outstanding items go back to the adviser, strategy is confirmed, work commences.Jason confirms the matching is right on the dummy pack.Not started

BASIS · TEAM HUDDLE

06 · THE PORTAL · PROPOSED MOCK-UP

PAGE 7 OF 15

The portal · proposed mock-up *

One screen. Simple enough that no one needs to be shown.

[basis-io]

Job number

BIO-2026-0142

Adviser · J. Carlos

1

Received

2

Checked

3

Tokenised

4

Ready

Client reference

Bob and Tracy · dummy pack

SoAR

SOA request · drop file

CPF

Client profile · drop file

Supporting docs

Statements, policies · drop files

Other

Anything that does not fit

Tell us about this job. What the client wants, what is missing, anything the paraplanner should know…

Captured by the local agent in the Airlock. Tokenised before it goes anywhere.

Send

Actions for this upload

Client reference entered

Upload SoAR

Upload CPF

Upload supporting documents

Add anything in Other

Confirm and send to the Airlock

Status comes back to this screen: received, checked, tokenised, ready. Outstanding items appear here too.

* Proposed mock-up. What this looks like is not decided yet.

BASIS · TEAM HUDDLE

07 · THE PRINCIPLES WE BUILD TO

PAGE 8 OF 15

The principles we build to

APP, SOC 1 and 2, ISO 27001.

FrameworkWhat it isWhat it means for this build
APPThe thirteen Australian Privacy Principles under the Privacy Act 1988.Collect only what the job needs. Redact and tokenise before anything is stored or sent to a model. Keep the key apart.
SOC 1An auditor’s report on controls over financial reporting.Every action logged with who, what and when, so a licensee’s auditor can follow a job end to end.
SOC 2An auditor’s report that security controls were in place and operated over a period.Access by policy, MFA on every login, change control on every code change, the log as the record.
ISO 27001The international standard for an information security management system.Name the controls as each piece is built, so the paperwork exists when a licensee asks.

Dummy data only until Damien is satisfied on all four.

BASIS · TEAM HUDDLE

08 · DEVELOPMENT TOOLS

PAGE 9 OF 15

Development tools

Development tools.

MICROSOFT

Az

Azure

The platform. One subscription, Australia East.

MICROSOFT

En

Entra External ID

Sign-in and MFA for advisers, paraplanners and licensees.

MICROSOFT · OPEN SOURCE

Pr

Presidio

Redaction and tokenisation. Task 2.

AZURE

KV

Key Vault

The Key Store. Token keys, access by policy. Task 3.

AZURE

CA

Container Apps

Runs Presidio and the local agent in the Airlock.

AZURE

Az

Blob, Functions, SQL

The Airlock and Vault stores, the job number, the log.

VERCEL

Vercel

Serves the portal screens. No client data on it.

GITHUB · ANTHROPIC

GitHub and Claude Code

Where the code lives and how it gets written.

The LLM behind the Vault agent is chosen during task 4. AI Foundry in Australia East is the likely route. Microsoft marks are placeholders until the logo files are supplied.

BASIS · TEAM HUDDLE

09 · DATES AND MILESTONES

PAGE 10 OF 15

Dates and milestones

Six dates. Marked off after each call. Last update 18 Oct, evening.

Changed on the call · 16 Oct · cadence agreed, dates stand

DateMilestoneWhat Jason and Damien seeStatus
Mon 20 OctAzure set up (done 18 Oct). Repo set up (done 18 Oct). Dummy pack from Jason.Nothing yet. Dean confirms by email.Done
Fri 31 OctTask 1. Portal upload working on dummy documents.A link. Upload the pack, see the status line.Not started
Fri 14 NovTasks 2 and 3. Redaction, tokenisation, key and job number.The tokenised copies of the pack beside the originals.Not started
Fri 28 NovTask 4. The two agents talking on tokens.A log of the exchange with no real value in it.Not started
Fri 12 DecTask 5. Matching and workflow in the Vault, first pass.Outstanding items and the summary on the dummy pack. Jason tests.Not started
Fri 19 DecReview. What works, what does not, plan for the new year.A short call. Damien’s view on the four principles.Not started

Two calls a week · to 19 Dec

Tuesday 11:30, one hour, Dean, Jason and Damien, from 20 October. Friday 11:30, thirty minutes, Dean and Damien, from 23 October.

In between

A Teams channel for questions, short videos and decisions. Reach out to each other whenever it is needed.

Why the pace

A working prototype in two to three weeks gives us the story for the pre-seed raise, then into the hands of customers and paraplanners.

BASIS · TEAM HUDDLE

FRIDAY 16 OCTOBER 2026

PAGE 11 OF 15

Next steps.

On the call

Agree the five tasks, the roles and the dates. Change anything that is wrong.

After the call

Done 16 October. Slides that moved carry a “changed on the call” tag. Same link.

Then

Dean starts on Azure and the portal. Jason sends the dummy pack and the document types. The Teams channel opens.

BASIS · TEAM HUDDLE

FRIDAY 16 OCTOBER 2026

PAGE 12 OF 15

Questions.

Open for discussion.

BASIS · TEAM HUDDLE

A1 · THE PLATFORM

PAGE 13 OF 15

Appendix · Glossary · The platform

The platform, by name.

TermWhat it meansWhere it is in this build
AirlockThe outer secured box. Everything that can identify a client stays inside it. Figure 1’s Phase 1 is its first container.Tasks 1 to 4. Azure, Australia East.
VaultInside the Airlock. Works on tokens and job numbers only. Never holds a key. Figure 1’s Phase 2 and 3.Task 5. Matching and workflow.
Key StoreWhere the token keys live. Azure Key Vault. Readable by the Airlock, not by the Vault.Task 3.
Evidentiary LayerFigure 1’s API layer, renamed. The semantic layer. Notes, logs, jobs, and the markdown file each agent writes when it retires.Task 4 writes the first agent files into it. The full layer is roadmap.
Advice WorkspaceFigure 1’s Workspace. Where the paraplanner works a job.Roadmap.
Compliance WorkspaceFigure 1’s Backend compliance. The licensee’s login, with its own agent.Roadmap.
Job numberThe number a job gets at the start. Every file, token and log entry carries it.Task 3.

BASIS · TEAM HUDDLE

A2 · DATA

PAGE 14 OF 15

Appendix · Glossary · Data

How client data is handled.

TermWhat it meansWhere it is in this build
PIIPersonally identifiable information. Anything that names a client or can be joined to name one.Found by Presidio in task 2.
RedactionRemoving a detail from a document entirely.Task 2, for details the job does not need.
TokenisationReplacing a detail with a placeholder that stands in for it, the same one every time it appears.Task 2: names, dates of birth, addresses, contacts, account numbers.
TokenThe placeholder itself. Means nothing without the key.Everything the Vault and the agents see.
Token keyThe list that maps each token back to its real value. Holding it is the same as holding the data.Task 3. Key Store only.
RehydrationPutting the real values back, using the key, so a person can read the file.Roadmap. Workspaces only, never the Vault.
Dummy dataInvented client files that look real and contain no real person. Jason’s Bob and Tracy pack.Every test in this phase.

BASIS · TEAM HUDDLE

A3 · MODELS AND TOOLS

PAGE 15 OF 15

Appendix · Glossary · Models and tools

Models and tools.

TermWhat it meansWhere it is in this build
Local agentA small language model running in our own container in Azure. Nothing leaves the resource group.Task 4, in the Airlock.
LLMA large language model run by a provider as a service. More capable. The data goes to that service, so region and terms matter.Task 4, the Vault agent. Sees tokens only.
AgentA model given a job, its files and its rules. It works through them, reports back, and is retired at sign-off. Its history goes to the Evidentiary Layer as a markdown file. Nothing stays alive.Task 4: one in the Airlock, one in the Vault.
PresidioMicrosoft’s open-source tool for finding and replacing PII in text and documents.Task 2.
Entra External IDMicrosoft’s sign-in service for customers and partners. Invite-only accounts, roles, MFA.Task 1, the portal login.